Tuesday, October 03, 2006
The crew from KC Construction continued their work on the first floor framing. They also started adding the plywood to the outside of the house.
A few of the Simpson Strong-Walls were delivered this morning. According to the structural drawings, there should be 11 of them of various sizes.
Brad
's trailer/office also arrived today!
posted by David @
4:00 PM
0 comments
0 Comments:
Post a Comment
<< Home
Previous Posts
If you had blinked, you would have missed it all!I...
I was at Costco this afternoon and happened to see...
There are piles of lumber in the back, ready for t...
We stopped by the job site this morning and saw Br...
Most of the lumber for the first floor framing was...
The framing contractors from KC Construction have ...
Here's a picture of Marc Ferrari (the Ferrari fami...
If you stop by the job site today, the first thing...
The framing contractors from KC Construction were ...
Ferma Corporation continued to work on the backfil...
0 Comments:
Post a Comment
<< Home