This morning Brad met with the contractors from Argonaut Window & Door. They started by placing all the windows and doors in the rooms where they are to be installed. Then they applied flashing around the openings for the windows.



A couple of contractors from Jim Giancola Concrete showed up around that time, to grind down some of the walls in preparation for stucco.

Back at home, I went through the entire window schedule to make a list of things I need to double check tomorrow. I need to check a CX14 near the front door that should have tempered glass. There are other CX14's in the house without tempered glass, so I want to make sure they installed the correct one by the front door. I also need to check the various sliding glass doors in the house -- I need to make sure they placed the door panels in the correct rooms. Many of the panels are the same size, but some of them have divided light and some of them do not.